W.T. Rich utilizes BIM-based 3-D modeling to conduct MEP coordination on all projects. We believe there are significant added value and cost savings through the use of BIM. Early planning during the preconstruction phase includes:
Clearly define subcontractor roles, responsibilities, standards and deadlines for the MEP coordination process
Manage data and information exchange standards
Provide baseline 3D architectural and structural models to each major trade discipline
Define and manage the schedule for coordination process
Schedule and lead regular MEP coordination meetings
Assemble and integrate contractor developed models
Run collision detection software
Lead MEP coordination efforts/meetings to investigate and resolve all conflicts
Catalog all coordination issues, along with their resolution
Verify that all agreed-to changes are properly captured in final models
Conduct regular field visits to verify that installation complies with coordination models